Summary
This project involved the construction of a new 1.6km access road for a newly proposed solar farm.
Robson were engaged to complete the following Scope of works:
- ~Clearing, grubbing and stripping of the site.
~Bulk earthworks including replacement of subgrade with select fill.
~Construction of drainage blankets to wet areas.
~Construction of pavement materials to access road, including sealed wearing course.
~Installation of multi cell under road drainage culverts
~Line marking and Signage Installation.
~Installation of fencing and gates.
~Seeding and landscaping.