PROJECT DETAILS
CLIENT: Xstrata Mangoola Pty Ltd
LOCATION: Mangoola, Hunter Valley, NSW
VALUE: $30m
DURATION: 12 months
Mangoola Coal Project CHPP Civil Works
Scope of Work
- Site clearance
- Design and construction of reinforced earth dump wall
- ROM Pad construction (1.2M bcm)
- Borrow pit materials management (500,000 tonne of select and 2.5 million tonne of general fill plus 250,000 tonne DGS/DGB)
- Haul roads construction
- Stormwater drainage including open drainage channels and pipe culverts
- Electrical and water services
- Sedimentation dam
Project Highlights
- Robson provided early contractor involvement to Xstrata with early mine planning assistance including site access assessments, bulk materials management planning and project feasibility analysis.
< Back